CUSD 308—Eastland High School

Project Name: CUSD 308—Eastland High School Additions and Renovations
Project Location: 500 South School Drive
Lanark, Illinois 60146
Project Type: Precast concrete and masonry field house addition including a new gymnasium, locker rooms, fitness center, Ag Classroom/Lab as well as sitework improvements. This work was completed while the building and campus were occupied by students and staff.
Project Architect: Bray Architects
Project Size: New work: 48,390 sf, Renovation: 3,700 sf
Client Name: Eastland CUSD 308
Construction Cost: $6.8 million
Contract Type: Construction Management